§2.4 · Making the weld
Welding-related calculations on the CWI
The CWI calculations area is shop math done by hand: heat input, fillet throat and cross-section, weld metal weight, deposition and cost, and unit conversions. The only help allowed is a four-function, construction or non-programmable scientific calculator (AWS CWI Examination User Guide, September 2026, checked October 2026).
- Exam
- CWI
- Clause
- §2.4
- Tags here
- 15
- Part A minimum
- at least 6%
2.4.1Formulas to carry in your head
| Quantity | Formula | Units to watch |
|---|---|---|
| Heat input | volts × amps × 60 ÷ travel speed | J/in with speed in in/min; ÷ 1,000 for kJ/in |
| Fillet throat | 0.707 × leg (equal-leg, flat face) | Same unit as the leg |
| Fillet cross-section | leg × leg ÷ 2 (equal-leg, flat face) | in²; reinforcement not counted |
| Weld metal weight | area × length × density | Length in inches if area is in in² |
| Deposition rate | weight deposited ÷ arc time | lb/h; count arc time only |
| Operating factor | arc time ÷ total time | Percent of the shift the arc is on |
| Deposition efficiency | weight deposited ÷ weight of electrode used | Percent; stubs and spatter are the loss |
| Length | 1 in = 25.4 mm | Exact; round only at the end |
| Temperature | °C = (°F − 32) × 5 ÷ 9 | Subtract 32 first |
| Stress | 1 ksi ≈ 6.895 MPa | 70 ksi ≈ 483 MPa |
Effective throat for strength can differ from the theoretical throat. The code you test on decides which one applies.
2.4.2What the math covers
The questions are short, but Part A is closed book with nothing on screen (AWS Part A information sheet, March 2024, checked October 2026), so every formula and conversion factor has to come from memory.
Calculators are inspected at check-in. Programmable, memory, alphabetical and noisy models aren't allowed. Bring a plain one you already know your way around. Parts A and C are taken at Prometric test centers with no online proctoring (AWS CWI page, checked October 2026); the rest of the setup is on CWI exam format.
Check units before arithmetic: travel speed per minute vs per second, joules vs kilojoules, inches vs millimeters, Fahrenheit vs Celsius. Heat input is where units bite hardest, so it has its own page, heat input.
Fractions on customary drawings
Customary drawings give sizes in fractions of an inch. Know the sixteenths as decimals without reaching for the calculator: 1/16 = 0.0625, 1/8 = 0.125, 3/16 = 0.1875, 1/4 = 0.25, 5/16 = 0.3125, 3/8 = 0.375. Convert to decimals first, then multiply.
Going metric and back
Conversions show up inside bigger questions. A 3/16 in root opening on a hypothetical drawing is 0.1875 × 25.4 = 4.76 mm. A 120°C limit on a hypothetical metric WPS is 120 × 9 ÷ 5 + 32 = 248°F. Do the conversion as its own line and the rest of the problem stays clean.
Two traps hide here. A metric WPS may give travel speed in mm/s. In that case the 60 drops out, and volts × amps ÷ speed gives J/mm directly. And a temperature difference converts without the 32: a 90°F rise is a 50°C rise, while 90°F as a reading is about 32°C.
Cost problems
Cost questions stack several small steps: labor and overhead per hour, how much weld metal goes down per hour of arc, the part of the shift the arc is actually on, and the filler itself. Write each piece with its unit, and the units cancel to dollars per pound or per foot. If they don't cancel, a step is missing.
2.4.3Worked through: heat input in kJ/mm
Write down what you have
A hypothetical pass at 25 V and 180 A, traveling 8 in/min. The WPS states its limit in kJ/mm.
Volts times amps
25 × 180 = 4,500 W. A watt is a joule per second.
Seconds to minutes
4,500 × 60 = 270,000 J per minute of arc time.
Divide by travel speed
270,000 ÷ 8 = 33,750 J/in, which is 33.75 kJ/in.
Switch to the WPS's unit
33.75 ÷ 25.4 = 1.33 kJ/mm. Compare that number against the limit.
Sanity-check the size
Leave out the 60 and you get 562.5 J/in, sixty times too small. That much off is a units slip; no real procedure runs that cold.
2.4.4Pencil math
Calculator out, units written down, then answer. The remarks show the working for every option, wrong ones included.
0 of 15 tagged · 0 accepted
Tag 01
Calculate the required argon gas flow rate (CFH) for a 1/8 inch tungsten electrode if the rule is 10 CFH per 1/16 inch of electrode diameter
Remarks on every option
- A 25 CFH would be 2.5 steps of 10. A 1/8 in tungsten is exactly two sixteenths.
- B 15 CFH is 1.5 steps. 1/8 in = 2/16 in, so it's 2 x 10.
- C Correct: 1/8 in = 2/16 in, so 2 x 10 CFH = 20 CFH.
- D 10 CFH covers 1/16 in only. A 1/8 in tungsten is twice that.
Pick an option. The remarks on all 4 open here.
Tag 02
Calculate the required filler metal weight for a 20-foot long V-groove weld if the deposition rate is 0.25 pounds per foot
Remarks on every option
- A Correct: 20 ft x 0.25 lb/ft = 5 lb.
- B 4.5 lb would be 18 ft at 0.25 lb/ft. Use the full 20 ft.
- C 4 lb would be 16 ft. Use the full 20 ft.
- D 5.5 lb overshoots. 20 x 0.25 is exactly 5.
Pick an option. The remarks on all 4 open here.
Tag 03
Calculate the required preheat time in minutes to reach 400°F if the heating rate is 15°F per minute starting from 70°F
Remarks on every option
- A 25 min is 375°F of rise. You only need 400 - 70 = 330°F.
- B 24 min is 360°F of rise, too much. The rise is 330°F.
- C 20 min is only 300°F, which leaves you at 370°F.
- D Correct: 400 - 70 = 330°F to gain; 330 ÷ 15 = 22 min.
Pick an option. The remarks on all 4 open here.
Tag 04
Calculate the maximum allowable amperage for a 3/32 inch tungsten electrode if the guideline is 1,600 amps per inch of electrode diameter.
Remarks on every option
- A 145 A comes from rounding 3/32 down. 3/32 in is exactly 0.09375 in.
- B 140 A is short. 0.09375 x 1,600 = 150 A.
- C 160 A would be a 0.1 in tungsten. 3/32 in is a bit smaller.
- D Correct: 3/32 in = 0.09375 in; 0.09375 x 1,600 = 150 A.
Pick an option. The remarks on all 4 open here.
Tag 05
If welding cost is $75/hour and deposition rate is 5 lbs/hr, what is the cost per pound of deposited weld metal?
Remarks on every option
- A Correct: $75 per hour ÷ 5 lb per hour = $15 per lb.
- B $18 doesn't come out of these numbers. $75 ÷ 5 is $15.
- C $20 would mean $100 an hour at 5 lb/h.
- D $12 would mean $60 an hour, or 6.25 lb/h.
Pick an option. The remarks on all 4 open here.
Tag 06
If welding operation costs are $85/hour and materials cost $25/lb, what is the total cost to deposit 4 lbs of weld metal at a deposition rate of 2 lbs/hour?
Remarks on every option
- A $255 is three hours of labor alone. You need 2 h of labor ($170) plus $100 of material.
- B Correct: 4 lb ÷ 2 lb/h = 2 h, so labor is 2 x $85 = $170. Material is 4 x $25 = $100. Total $270.
- C $240 is short. Labor is $170 and material $100.
- D $285 overcounts. $170 labor + $100 material = $270.
Pick an option. The remarks on all 4 open here.
Tag 07
What is the electrode efficiency if 8 pounds of electrode produces 6.4 pounds of deposited weld metal?
Remarks on every option
- A 85% would mean 6.8 lb deposited.
- B Correct: 6.4 ÷ 8 = 0.80, so 80% of the electrode ended up as weld metal.
- C 75% would mean 6.0 lb deposited.
- D 70% would mean 5.6 lb deposited.
Pick an option. The remarks on all 4 open here.
Tag 08
If a welder deposits 5 pounds of weld metal in 2 hours, what is the deposition rate in pounds per hour?
Remarks on every option
- A Correct: 5 lb ÷ 2 h = 2.5 lb/h.
- B 5 lb/h is the total, not divided over the 2 hours.
- C 3 lb/h would be 6 lb in 2 hours.
- D 2 lb/h would be 4 lb in 2 hours.
Pick an option. The remarks on all 4 open here.
Tag 09
If the welding arc time is 6 minutes out of a 10-minute period, what is the duty cycle?
Remarks on every option
- A 55% would be 5.5 min of arc time.
- B 65% would be 6.5 min of arc time.
- C 50% would be 5 min of arc time.
- D Correct: 6 ÷ 10 = 60%. Duty cycle is figured on a 10-minute period.
Pick an option. The remarks on all 4 open here.
Tag 10
Calculate the included angle needed for a V-groove weld if each bevel angle is 35 degrees
Remarks on every option
- A 60° would mean 30° bevels.
- B 80° would mean 40° bevels.
- C 75° would mean 37.5° bevels.
- D Correct: The included angle is both bevels added: 35° + 35° = 70°.
Pick an option. The remarks on all 4 open here.
Tag 11
Calculate the required gas flow rate in L/min if the current specification is 35 CFH (Cubic Feet per Hour)
Remarks on every option
- A 15.75 L/min is too low. One cubic foot is about 28.3 L, so 35 CFH is about 991 L per hour; divide that by 60.
- B Correct: 35 ft³/h × 28.32 L/ft³ ≈ 991 L/h, and 991 ÷ 60 ≈ 16.52 L/min.
- C 17.25 L/min is too high. Use 28.32 L per cubic foot and divide the hourly volume by 60 minutes.
- D 18.00 L/min overshoots. With 28.32 L per cubic foot, 35 CFH works out to about 16.5 L/min.
Pick an option. The remarks on all 4 open here.
Tag 12
Calculate the required gas volume in cubic feet for a 4-hour welding shift if flow rate is 40 CFH and arc time is 65%
Remarks on every option
- A 100 cu ft is about 2.5 h of arc. 65% of 4 h is 2.6 h.
- B Correct: Arc time is 4 h x 0.65 = 2.6 h; 2.6 x 40 CFH = 104 cu ft.
- C 110 cu ft is too high. 2.6 h x 40 = 104.
- D 95 cu ft is short. Gas flows during arc time: 2.6 h x 40 = 104.
Pick an option. The remarks on all 4 open here.
Tag 13
Calculate the overlap percentage if the weld bead width is 0.5 inches and the step increment is 0.3 inches
Remarks on every option
- A Correct: Each bead overlaps the last by 0.5 - 0.3 = 0.2 in; 0.2 ÷ 0.5 = 40%.
- B 45% would need a 0.275 in step.
- C 50% would need a 0.25 in step, half the bead width.
- D 35% would need a 0.325 in step.
Pick an option. The remarks on all 4 open here.
Tag 14
If a welding machine uses 35 volts and 175 amps, what is the power consumption in kilowatts?
Remarks on every option
- A Correct: 35 V x 175 A = 6,125 W = 6.125 kW.
- B 6.5 kW is too high. 35 x 175 = 6,125 W.
- C 6.25 kW is 125 W too high. 35 x 175 = 6,125 W.
- D 5.875 kW is 250 W short. 35 x 175 = 6,125 W.
Pick an option. The remarks on all 4 open here.
Tag 15
Calculate the weld metal weight in pounds needed for a 30-foot long, 1/4 inch fillet weld if the density is 0.28 lbs/cubic inch
Remarks on every option
- A 3.45 lb overshoots. A 1/4 in fillet's cross-section is ½ x 0.25 x 0.25 = 0.03125 sq in.
- B 3.75 lb is too much. 0.03125 sq in x 360 in = 11.25 cu in.
- C 2.85 lb is short. 11.25 cu in x 0.28 = 3.15 lb.
- D Correct: Area = ½ x 0.25² = 0.03125 sq in; x 360 in = 11.25 cu in; x 0.28 lb/cu in = 3.15 lb.
Pick an option. The remarks on all 4 open here.
2.4.5Sources
- AWS CWI Examination User Guide, September 2026 — calculators allowed in the test room (checked October 2026)
- AWS Part A information sheet, March 2024 — Part A is closed book (checked October 2026)
- AWS CWI page — Parts A and C at Prometric centers (checked October 2026)
Keep it in your pocket
Got an iPhone or iPad? Our CWI prep app keeps practice questions on hand when you're nowhere near a desk.